What is the standard for the rebound rate of tunnel shotcrete?
The rebound rate of shotcrete in tunnel projects is generally 30%, which is a big loss. Through technical improvement and strengthened management, the rebound rate of shotcrete can be controlled to about 20%. The side wall is not more than 15%, and the top arch is not more than 25%.
Shotcrete is a construction method of spraying fine stone concrete with a pressure spray gun. The rebound rate of the spraying needs to be measured by pre-buried monitoring instruments, such as rebound testers.